Images .. Source: JAKT transferred the platform of the Baltim field and reduced the installation time
An official source in the oil sector said that Petrojet has completed the relocation of the Belt field platform to the field site, pointing out that the platform is being installed. The lengths of the platform mounts have been adjusted to be fitted with one piece, which reduces 4 days of installation time at sea.
.jpg)
The source added in a special statement to "the seventh day" that the adjustment of the lengths of the platform carriers to be installed one piece will save from the cost of installation, pointing out that it is planned to finish installation Jakt today.
.jpg)
The source pointed out that after the completion of the installation will be the installation of production facilities on the platform and the entry of the project on production, as planned to achieve a breakthrough in Egypt's production of gas rich in condensate, which allows the expansion of the production of many products such as butane, propane and others.
.jpg)
It is worth mentioning that the platform of the field of Baltim was manufactured for the company Petrobal, and the installation work will be 18 kilometers from the Mediterranean coast and a depth of 25 meters and a weight of 5870 tons.
.jpg)
With regard to the field of West Baltim, will be tied to production mid-year production capacity will reach about 500 million cubic feet per day of natural gas during the second half of June, and will be linked to production facilities Abu Madi 26-inch sea line and a length of 25 kg .
.jpg)
.jpg)