Information on the implementation of the natural gas network in the government district in the administrative capital

The aim of accelerating the delivery of gas to the new projects is to meet the needs of the continuous urban expansion of natural gas services as distinct civilizational services. In April, the protocol of implementation of the natural gas network in the government district was signed in the new administrative capital. The following are the top 6 information on the implementation of this network, As follows:
1- The investment cost is LE 31.5 million for the implementation of the necessary infrastructure for the delivery of natural gas to the buildings of state institutions in the government districts.
2 – The launch of natural gas to the government district in the new administrative capital is scheduled after the completion of the work of implementing the necessary infrastructure to deliver the gas according to the time plan set.
3- The Ministry of Petroleum shall give payments to implement quick work programs to deliver natural gas to all vital national projects implemented by the State at present in rapid and disciplined steps in the framework of advancing comprehensive development.
4 – Implementation of the natural gas network of the government sector in the first phase of the administrative capital aims to connect the service to the buildings of the ministries of the government on an area of 153 acres and buildings of major state institutions.
5 – Cooperation with the Ministry of Petroleum includes the implementation of the cooling plant with natural gas and the implementation of the main gas network and gas pressure reduction station in the administrative capital.
6. The natural gas delivery project for the government garden will be implemented at a rapid pace, including four main axes, some of which will be parallel to each other. The project will start with the preparation of the studies and the necessary measurements to start the work in the implementation area and supply all the necessary tasks and requirements for the completion of the project. 10 and 32 km to feed the government district natural gas, and provide all the engineering and technical personnel specialized to complete the implementation on time while maintaining the maximum rates of security and safety.