Conditions that must be met for obtaining a permit to demolish facilities that fall

Some real estate owners resort to obtaining demolition permits to demolish buildings that have been demolished, to demolish the property before it collapses on the population because of its depletion or because it has become a fall, but there are conditions and criteria that must be obtained for obtaining the permit before the demolition begins. On the demolition permit.
"Seventh Day" explains the following in the following lines the most important criteria, conditions and documents required by the district officials of real estate owners who fall before obtaining a license to demolish the facility to fall as follows:
First, the criteria for obtaining a license to demolish facilities that fall
1. The applicant must be the owner of the property or a business agent under a formal authorized agent
2 – There are no irregularities or late dues
Second, the required documents
1- Copy of the national ID card of the applicant
2. A final demolition order issued by the administrative authority in accordance with Articles 90 and 92 of the Law
3- A report from a construction engineer with at least 7 years of experience, explaining the method used to carry out the demolition and the necessary precautions to ensure occupants, passersby and neighboring facilities.
Third, the fees paid for the license
1-Pay check fee 20 pounds
2 – Fee of issuing 200 pounds per role up to a maximum of 1000 pounds, and this fee increases 3% per annum as of February 2009
3. Insurance 2.0% of the value of the business to be licensed
4 – Engineering impressions 5.1% of the value of the works submitted
5 – Drawing development resources 10 piasters
6-Tax quality 60 pounds